Multiple Choice
If resources are to be considered in planning, it is necessary to
A) know when each is taking vacation time or time off.
B) know the name of each resource on the project.
C) list all the projects to which the resources have been assigned.
D) indicate the amounts and types of resources needed to perform each activity.
Correct Answer:

Verified
Correct Answer:
Verified