Multiple Choice
Resource utilisation charts based on each activity's earliest start time are said to be based on
A) availability times.
B) an as-late-as-possible (ALAP) schedule.
C) an as-soon-as-possible (ASAP) schedule.
D) a limited schedule plan.
Correct Answer:

Verified
Correct Answer:
Verified