Solved

-Resource Levelling, or Smoothing, Is a Method for

Question 18

Multiple Choice

  -Resource levelling, or smoothing, is a method for A) developing a schedule that attempts to minimise the fluctuations in requirements for resources. B) making sure all the resources do the same amount of work. C) making sure every task has the same number of resources. D) extending the project to have the least number of resources used per day.
-Resource levelling, or smoothing, is a method for


A) developing a schedule that attempts to minimise the fluctuations in requirements for resources.
B) making sure all the resources do the same amount of work.
C) making sure every task has the same number of resources.
D) extending the project to have the least number of resources used per day.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions