Multiple Choice
Total slack for the project is the difference between
A) LF time of last activity and the project required completion time.
B) EF time of last activity and the project required completion time.
C) ES time of last activity and the project required completion time.
D) LS time of last activity and the project required completion time.
Correct Answer:

Verified
Correct Answer:
Verified