Multiple Choice
The facilitator for the scrum development process during a sprint whose primary job is to take actions to remove or reduce any obstacles, barriers, or constraints that are impeding progress of the development team toward achieving their work tasks and that may negatively impact the successful production and demonstration of a deliverable working product increment by the end of the sprint time is the
A) scrum master.
B) project manager.
C) product owner.
D) sprint timer.
Correct Answer:

Verified
Correct Answer:
Verified
Q18: When the customer requests a change, the
Q31: Project management is a proactive approach to
Q32: Latest start time is calculated by<br>A)subtracting the
Q35: As a part of the scrum technique
Q37: The project team member also referred to
Q38: Free slack is the amount of time
Q51: Changes requested early in the project always
Q66: Calculate the latest start for Task D
Q101: This longest path in the overall network
Q109: The estimated resources required for an activity