Multiple Choice
Latest start time is calculated by
A) subtracting the activity's estimated duration from the activity's succeeding activity's latest finish time: LS = LF succeeding activity - estimated duration.
B) adding the activity's estimated duration to the predecessor of the activity's latest start time: LS = LS predecessor + estimated duration.
C) subtracting the activity's estimated duration from the activity's latest finish time: LS = LF - estimated duration.
D) adding the activity's estimated duration to the activity's latest finish time: LS = LF + estimated duration.
Correct Answer:

Verified
Correct Answer:
Verified
Q4: The key to effective project control is
Q18: When the customer requests a change, the
Q31: Project management is a proactive approach to
Q33: The facilitator for the scrum development process
Q35: As a part of the scrum technique
Q37: The project team member also referred to
Q38: Free slack is the amount of time
Q51: Changes requested early in the project always
Q66: Calculate the latest start for Task D
Q101: This longest path in the overall network