Multiple Choice
The project team member also referred to as the customer representative and responsible for defining the customer requirements and product features and for ensuring that the development team delivers an end product with the required features is the
A) scrum master.
B) project manager.
C) product owner.
D) sprint timer.
Correct Answer:

Verified