Multiple Choice
During a project assessment, a project manager determines the initial project cost estimates were incorrect, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take?
A) Alert the project sponsor of the situation.
B) Contact the customer and request more funding.
C) Announce the project will end early due to lack of funds.
D) Attempt to save money in downstream activities.
Correct Answer:

Verified
Correct Answer:
Verified
Q387: A diagram or chart is required to
Q388: During planning, a project coordinator publishes the
Q389: A company is in the process of
Q390: Team members have reported poor sound quality
Q391: A project manager is managing a project
Q393: Severe weather has impacted a construction project,
Q394: A minor change to the baseline schedule
Q395: A project team is defining detailed risks.
Q396: An employee is assigned to a project
Q397: Due to a lack of adherence to