Solved

Due to a Lack of Adherence to the Risk Response

Question 397

Multiple Choice

Due to a lack of adherence to the risk response plan, there are numerous safety concerns within the scope of a building project. Which of the following MOST likely explains this issue?


A) Risks were not identified.
B) Risks were not mitigated.
C) Risks were not exploited.
D) Risks were not communicated.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge