Question 396

Multiple Choice

An employee is assigned to a project and is developing a project charter. Which of the following are some of the constraints the employee would typically face at this stage of the project?


A) Environment, resources, requirements, and quality
B) Budget, quality, resources, and schedule
C) Deliverables, scope, and budget environment
D) Budget, scope, quality, and schedule