Multiple Choice
Severe weather has impacted a construction project, delaying scheduled work for five days. Which of the following project changes is the project manager most likely to consider FIRST?
A) Requirements change
B) Funding change
C) Timeline change
D) Risk event
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q388: During planning, a project coordinator publishes the
Q389: A company is in the process of
Q390: Team members have reported poor sound quality
Q391: A project manager is managing a project
Q392: During a project assessment, a project manager
Q394: A minor change to the baseline schedule
Q395: A project team is defining detailed risks.
Q396: An employee is assigned to a project
Q397: Due to a lack of adherence to
Q398: Which of the following is used to