menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Certification
  3. Study Set
    Computing Technology Industry Association (CompTIA)
  4. Exam
    Exam 11: CompTIA Project+
  5. Question
    Which of the Following Is a Schedule That Illustrates the Duration
Solved

Which of the Following Is a Schedule That Illustrates the Duration

Question 347

Question 347

Multiple Choice

Which of the following is a schedule that illustrates the duration of an activity?


A) Process diagram
B) Ishikawa diagram
C) Gantt chart
D) Pareto chart

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q342: A carpenter on a project team reports

Q343: A customer has requested a new feature

Q344: The project manager for a TV tower

Q345: A project sponsor approaches the project manager

Q346: A project manager needs status on the

Q348: Communication on a project is flowing well.

Q349: A Chief Executive Officer (CEO) has approached

Q350: A customer is in the early planning

Q351: A project manager is working on the

Q352: A key stakeholder cannot identify within the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines