Multiple Choice
A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?
A) Analyze the critical path and update the WBS with the new feature
B) Add the new feature and reprioritize the product backlog
C) Add the new feature to the next sprint and move the old feature to the following sprint
D) Conduct a retrospective with the team to discuss the change and introduce the feature
Correct Answer:

Verified
Correct Answer:
Verified
Q338: The client accepts the critical design review.
Q339: Which of the following resources outlines consequences
Q340: A project manager wants to introduce the
Q341: A project manager is scheduling activities and
Q342: A carpenter on a project team reports
Q344: The project manager for a TV tower
Q345: A project sponsor approaches the project manager
Q346: A project manager needs status on the
Q347: Which of the following is a schedule
Q348: Communication on a project is flowing well.