Question 319

Multiple Choice

A project team added a new member who has proprietary information about a competitor's product. The team member was suddenly removed from the project. Which of the following MOST likely occurred?


A) The company received a C&D.
B) A higher-priority project needed the expertise.
C) The new member did not sign an NDA.
D) An SLA prevented new team members.