Multiple Choice
While starting a new project, management is aligning the project to the organization's strategy, assigning limited resources based upon priorities, and optimizing resource deployment between projects. Which of the following BEST describes these actions?
A) Portfolio management
B) Agile management
C) Project management
D) Strategic management
Correct Answer:

Verified
Correct Answer:
Verified