Multiple Choice
A project coordinator logs potential events that can affect project constraints, and then records the results of brainstorming of potential strategies. Which of the following documents should the project coordinator use?
A) Risk register
B) Issue log
C) Communication plan
D) Status report
Correct Answer:

Verified
Correct Answer:
Verified