    A Project Manager Needs to Identify the Resources Assigned to a Particular
Solved

A Project Manager Needs to Identify the Resources Assigned to a Particular

Question 115

Question 115

Multiple Choice

A project manager needs to identify the resources assigned to a particular task. In which of the following documents can this information be found?


A) Project schedule
B) Cost plan
C) Scope statement
D) Impact assessment

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q110: Which of the following are characteristics of

Q111: A client has provided a list of

Q112: The project manager is running a project

Q113: A vendor advises the project manager that

Q114: A non-stakeholder approaches the project manager and

Q116: A project coordinator logs potential events that

Q117: Which of the following represents the order

Q118: During the planning phase, the project manager

Q119: During an ad-hoc meeting, the PM notifies

Q120: Project cost control deals with:<br>A) controlling residual

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines