Multiple Choice
During an ad-hoc meeting, the PM notifies the sponsor that while the project is on schedule, material costs have increased and the project is over budget. To save the project, the PM request a material contract with a less expensive vendor. The sponsor approves the change, and project comes in within target tolerances. The company, however, receives numerous stakeholder complaints. Which of the following is the MOST likely cause of these complaints?
A) The quality of the deliverable decreased due to the rising material cost.
B) The PM did not follow the project communication plan.
C) Quality assurance actions were not adjusted for the vendor change.
D) The change was not documented and approved.
Correct Answer:

Verified
Correct Answer:
Verified
Q114: A non-stakeholder approaches the project manager and
Q115: A project manager needs to identify the
Q116: A project coordinator logs potential events that
Q117: Which of the following represents the order
Q118: During the planning phase, the project manager
Q120: Project cost control deals with:<br>A) controlling residual
Q121: A project team is comprised of a
Q122: A project manager is creating the WBS.
Q123: A project manager is attempting to establish
Q124: A project stakeholder approaches the project manager