Multiple Choice
During the planning phase, the project manager meets with the project team to determine the tasks and their relationship. Which of the following should the project manager receive from the team members? (Choose two.)
A) Durations
B) Start/finish dates
C) Dependencies
D) Resources
E) Baseline
Correct Answer:

Verified
Correct Answer:
Verified
Q113: A vendor advises the project manager that
Q114: A non-stakeholder approaches the project manager and
Q115: A project manager needs to identify the
Q116: A project coordinator logs potential events that
Q117: Which of the following represents the order
Q119: During an ad-hoc meeting, the PM notifies
Q120: Project cost control deals with:<br>A) controlling residual
Q121: A project team is comprised of a
Q122: A project manager is creating the WBS.
Q123: A project manager is attempting to establish