Multiple Choice
A project manager is scheduling activities and determines one activity cannot be completed until another activity is completed. Which of the following dependency relationships is represented?
A) FF
B) SS
C) SF
D) FS
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q336: The project manager was asked to provide
Q337: Which of the following is the MOST
Q338: The client accepts the critical design review.
Q339: Which of the following resources outlines consequences
Q340: A project manager wants to introduce the
Q342: A carpenter on a project team reports
Q343: A customer has requested a new feature
Q344: The project manager for a TV tower
Q345: A project sponsor approaches the project manager
Q346: A project manager needs status on the