Multiple Choice
During the testing phase, a team member has informed the project manager that the test environment was set with inadequate client information, putting the project in jeopardy. Which of the following should the project manager do NEXT?
A) Ask the team member to move to a different test environment.
B) Ask the team member to refrain from testing the scenarios.
C) Revisit the risk management plan and provide corrective actions.
D) Revisit the contingency plan and provide corrective actions.