Question 49

Multiple Choice

Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) project (activity completion times are in days) .
Use this information to answer the following questions. Consider the following Activity-On-Node (AON) project (activity completion times are in days) .    -Refer to the figure.What is the slack time,in days,associated with activity D? A) 0 B) 1 C) 2 D) 3 E) 4
-Refer to the figure.What is the slack time,in days,associated with activity D?


A) 0
B) 1
C) 2
D) 3
E) 4