Multiple Choice
Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) project (activity completion times are in days) .
-Refer to the figure.What is the slack time,in days,associated with activity D?
A) 0
B) 1
C) 2
D) 3
E) 4
Correct Answer:

Verified
Correct Answer:
Verified