Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) PERT project.The three values that represent each activity's completion time (in days) correspond to an optimistic time,most likely time,and pessimistic time,respectively.
-Refer to the figure.What is the expected completion time of activity A?
A) 3
B) 4
C) 5
D) 2) 7
E) 2) 5
Correct Answer:

Verified
Correct Answer:
Verified