Multiple Choice
Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) project (activity completion times are in days) .
-Refer to the figure.What are the immediate successor(s) of activity C?
A) D
B) E
C) D and E
D) A
E) B and D
Correct Answer:

Verified
Correct Answer:
Verified