Solved

Use This Information to Answer the Following Questions -Refer to the Information Above

Question 21

Essay

Use this information to answer the following questions.
Consider the following set of activities that need to be completed by a chef to cook dinner for a party of 30 guests.
 Immediate  Activity  Predecessors  A  B  A  C  A  D  B, C  E  C  F  D, E \begin{array} { c l l } & \text { Immediate } \\\text { Activity } & \text { Predecessors } \\\hline \text { A } & - \\\text { B } & \text { A } \\\text { C } & \text { A } \\\text { D } & \text { B, C } \\\text { E } & \text { C } \\\text { F } & \text { D, E }\end{array}
-Refer to the information above.Assume that the chef was able to estimate the number of hours needed to complete each activity as follows.
 Activity  Optimistic time  Most Likely Time  Pessimistic Time  A 123 B 122 C 234 D 356 E 456 F 367\begin{array} { c c c c } \text { Activity } & \text { Optimistic time } & \text { Most Likely Time } & \text { Pessimistic Time } \\\text { A } & 1 & 2 & 3 \\\text { B } & 1 & 2 & 2 \\\text { C } & 2 & 3 & 4 \\\text { D } & 3 & 5 & 6 \\\text { E } & 4 & 5 & 6 \\\text { F } & 3 & 6 & 7\end{array}
a.Use PERT to identify the expected time and variance for each activity.
b.What is the critical path?
c.What is the expected time and variance of the critical path?
d.Determine the expected completion time of the project.

Correct Answer:

verifed

Verified

\[\begin{array} { | c | c | c | c | c | ...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions