Question 1

Essay

Use this information to answer the following questions.
Consider the following set of activities that need to be completed by a chef to cook dinner for a party of 30 guests.
 Immediate  Activity  Predecessors  A  B  A  C  A  D  B, C  E  C  F  D, E \begin{array} { c l l } & \text { Immediate } \\\text { Activity } & \text { Predecessors } \\\hline \text { A } & - \\\text { B } & \text { A } \\\text { C } & \text { A } \\\text { D } & \text { B, C } \\\text { E } & \text { C } \\\text { F } & \text { D, E }\end{array}
-Refer to the information above.Assume that the chef was able to estimate the number of hours needed to complete each activity as follows.
 Activity  Optimistic time  Most Likely Time  Pessimistic Time  A 123 B 122 C 234 D 356 E 456 F 367\begin{array} { c c c c } \text { Activity } & \text { Optimistic time } & \text { Most Likely Time } & \text { Pessimistic Time } \\ \text { A } & 1 & 2 & 3 \\\text { B } & 1 & 2 & 2 \\\text { C } & 2 & 3 & 4 \\\text { D } & 3 & 5 & 6 \\\text { E } & 4 & 5 & 6 \\\text { F } & 3 & 6 & 7\end{array}
Determine the probability that the project will be completed in
a.Less than 14 hours.
b.Greater than 14 hours.
c.Less than 17 hours.
d.Greater than 17 hours.