Multiple Choice
With a Differing Site Condition, the Contract Administrator should
A) fully document all aspects of the different condition
B) meet as quickly as possible to brainstorm solutions
C) notify all parties immediately
D) all of these
Correct Answer:

Verified
Correct Answer:
Verified
Q2: A Type I Differing Site Condition is
Q3: Reliance upon the Spearin Doctrine is sufficient
Q4: In order to avoid responsibility, the Owner
Q5: Type I Differing Site Conditions should have
Q6: Acting conscionably means to act prudently in
Q7: Type II Differing Site Conditions<br>A) differ from
Q8: Type I Differing Site Conditions<br>A) differ from
Q9: If there is an exculpatory clause protecting
Q10: With a Differing Site Condition<br>A) the Contract
Q11: Differing Site Conditions usually refers to something