Multiple Choice
If a change affects the schedule
A) the Owner and Architect will know
B) the Contract Administrator should document and notify the Architect and Owner
C) pricing of the change should be submitted immediately
D) a solution must first be found before notifying all concerned
Correct Answer:

Verified
Correct Answer:
Verified