Characteristic of a Critical Path Schedule is
A) there can be float on all but the critical path itself
B) only the critical portion of the project is what is shown so everyone can concentrate on that section
C) it eliminates the need for Constructive Acceleration
D) it eliminates the need for directed acceleration
Correct Answer:

Verified
Correct Answer:
Verified