Constructive changes
A) have a positive effect on the morale of the workforce
B) always make the Constructor a reasonable profit
C) may seem insignificant when first asked for by the Owner, but they can require additional cost and time as they are performed
D) do not require notice since they would be documented by the actual work constructed
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Fast tracking is one method to shorten
Q3: Characteristic of a Critical Path Schedule is<br>A)
Q4: Ambiguities will always be ""construed against the
Q5: Without a change order clause in the
Q6: If a change affects the schedule<br>A) the
Q8: A Patent Ambiguity is one that no
Q9: Float on the critical path gives everyone
Q10: The Eichleay formula was developed for<br>A) private
Q11: Fortunately, Constructive Acceleration guarantees the Contractor will
Q12: Constructive changes can seemingly be clarification of