The Project Planning and Estimating Process (Circle All That Apply)

Question 2

Multiple Choice

The project planning and estimating process (circle all that apply) :


A) uses a top-down approach to disseminate information about project goals to lower levels
B) uses a bottom up approach to prepare and check labor and cost estimates
C) employs pricing units to decide on areas of work needed and to prepare labor hour estimates
D) relies upon work package supervisors to authorize when work packages should begin

Correct Answer: