Multiple Choice
Which of the following statements are true about cost estimating (circle all that are true) :
A) the expert opinion method is the same as the cost engineering method
B) the analogy method requires that a similar project or work task was done previously
C) the parametric method is an estimate based on a mathematical formula
D) the analogy method can take into account differences between projects
Correct Answer:

Verified
Correct Answer:
Verified