menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management for Engineering
  4. Exam
    Exam 8: Advanced Project Network Analysis and Scheduling
  5. Question
    If a = 3, M = 5, and B =
Solved

If a = 3, M = 5, and B =

Question 2

Question 2

Multiple Choice

If a = 3, m = 5, and b = 6, then:


A) te = 4.667 and V = 1.5
B) te = 4.833 and V = 0.5
C) neither

Correct Answer:

verifed

Verified

Related Questions

Q1: The following type of buffer does not

Q3: GERT (circle all that are true):<br>A) utilizes

Q4: Resource buffers are always placed:<br>A) on the

Q5: Statement: The cost slope is the marginal

Q6: Statement: Given the assumptions of PERT, it

Q7: To reduce the duration of a project

Q8: Statement: In the critical path method (CPM),

Q9: Statement: It is relatively easy to level

Q10: To find the shortest possible project duration

Q11: Statement: Although the times used in PERT

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines