Multiple Choice
Resource buffers are always placed:
A) on the critical chain only
B) on both critical and on non-critical paths
C) where non-critical paths merge into the critical chain
D) at the end of the critical chain
E) at places where a "count down" to the start of a non-critical activity is needed.
Correct Answer:

Verified
Correct Answer:
Verified