True/False
Statement: In the critical path method (CPM), the direct cost of an activity is assumed to be proportional to its time, so shortening it to its "crash" time reduces its cost.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q3: GERT (circle all that are true):<br>A) utilizes
Q4: Resource buffers are always placed:<br>A) on the
Q5: Statement: The cost slope is the marginal
Q6: Statement: Given the assumptions of PERT, it
Q7: To reduce the duration of a project
Q9: Statement: It is relatively easy to level
Q10: To find the shortest possible project duration
Q11: Statement: Although the times used in PERT
Q12: The Following Questions adapted from tutorial material
Q13: An approach to accelerate a project by