Multiple Choice
To find the shortest possible project duration for the least cost:
A) crash all activities on the critical path (CP) , then relax all non-CP activities
B) crash all activities not on the CP, then relax all critical activities
C) crash all activities in the project, then relax those not on the CP
D) crash all activities in the project, then relax those on the critical path