Multiple Choice
In a network, the critical path is that sequence of activities that requires:
A) the longest time to complete
B) the shortest time to complete
C) both a and b
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q10: If an activity has two immediate successors
Q11: Use the table and network below
Q12: The early expected start time, ES, of
Q13: Statement: The term "dummy activity" is a
Q14: Statement: If an activity has multiple predecessors,
Q16: Level the resources for the activities below:
Q17: Which one of the following statements is
Q18: Doing a project fast has the following
Q19: Statement: The total slack of each of
Q20: Statement: The free slack of each of