Solved

Use the Table and Network Below to Answer Parts (A)

Question 11

Short Answer

Use the table and network below to answer parts (a) through (d).
 Activity  Time  (Weeks)  Weekly  Cost ($ K)  Total ($ K) A 5210 B 8324 C 6424 D 339 E 428 F 31378\begin{array} { c | c | c | c } \text { Activity } & \begin{array} { c } \text { Time } \\\text { (Weeks) }\end{array} & \begin{array} { c } \text { Weekly } \\\text { Cost (\$ K) }\end{array} & \begin{array} { c } \text { Total } \\( \$ \mathrm {~K} )\end{array} \\\hline \text { A } & 5 & 2 & 10 \\\text { B } & 8 & 3 & 24 \\\text { C } & 6 & 4 & 24 \\\text { D } & 3 & 3 & 9 \\\text { E } & 4 & 2 & 8 \\\text { F } & 3 & 1 & \underline{3} \\& & & 78\end{array}  Use the table and network below to answer parts (a) through (d).   \begin{array} { c | c | c | c }  \text { Activity } & \begin{array} { c }  \text { Time } \\ \text { (Weeks) } \end{array} & \begin{array} { c }  \text { Weekly } \\ \text { Cost (\$ K) } \end{array} & \begin{array} { c }  \text { Total } \\ ( \$ \mathrm {~K} ) \end{array} \\ \hline \text { A } & 5 & 2 & 10 \\ \text { B } & 8 & 3 & 24 \\ \text { C } & 6 & 4 & 24 \\ \text { D } & 3 & 3 & 9 \\ \text { E } & 4 & 2 & 8 \\ \text { F } & 3 & 1 & \underline{3} \\ & & & 78 \end{array}    (a) On the network above, show ES, EF, LS, and LF for every event.  (b) Below, construct a Gantt chart for the network using only ES's and EF's.    (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.    (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.     (a) On the network above, show ES, EF, LS, and LF for every event.
(b) Below, construct a Gantt chart for the network using only ES's and EF's.
 Use the table and network below to answer parts (a) through (d).   \begin{array} { c | c | c | c }  \text { Activity } & \begin{array} { c }  \text { Time } \\ \text { (Weeks) } \end{array} & \begin{array} { c }  \text { Weekly } \\ \text { Cost (\$ K) } \end{array} & \begin{array} { c }  \text { Total } \\ ( \$ \mathrm {~K} ) \end{array} \\ \hline \text { A } & 5 & 2 & 10 \\ \text { B } & 8 & 3 & 24 \\ \text { C } & 6 & 4 & 24 \\ \text { D } & 3 & 3 & 9 \\ \text { E } & 4 & 2 & 8 \\ \text { F } & 3 & 1 & \underline{3} \\ & & & 78 \end{array}    (a) On the network above, show ES, EF, LS, and LF for every event.  (b) Below, construct a Gantt chart for the network using only ES's and EF's.    (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.    (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.     (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.
 Use the table and network below to answer parts (a) through (d).   \begin{array} { c | c | c | c }  \text { Activity } & \begin{array} { c }  \text { Time } \\ \text { (Weeks) } \end{array} & \begin{array} { c }  \text { Weekly } \\ \text { Cost (\$ K) } \end{array} & \begin{array} { c }  \text { Total } \\ ( \$ \mathrm {~K} ) \end{array} \\ \hline \text { A } & 5 & 2 & 10 \\ \text { B } & 8 & 3 & 24 \\ \text { C } & 6 & 4 & 24 \\ \text { D } & 3 & 3 & 9 \\ \text { E } & 4 & 2 & 8 \\ \text { F } & 3 & 1 & \underline{3} \\ & & & 78 \end{array}    (a) On the network above, show ES, EF, LS, and LF for every event.  (b) Below, construct a Gantt chart for the network using only ES's and EF's.    (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.    (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.     (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.
 Use the table and network below to answer parts (a) through (d).   \begin{array} { c | c | c | c }  \text { Activity } & \begin{array} { c }  \text { Time } \\ \text { (Weeks) } \end{array} & \begin{array} { c }  \text { Weekly } \\ \text { Cost (\$ K) } \end{array} & \begin{array} { c }  \text { Total } \\ ( \$ \mathrm {~K} ) \end{array} \\ \hline \text { A } & 5 & 2 & 10 \\ \text { B } & 8 & 3 & 24 \\ \text { C } & 6 & 4 & 24 \\ \text { D } & 3 & 3 & 9 \\ \text { E } & 4 & 2 & 8 \\ \text { F } & 3 & 1 & \underline{3} \\ & & & 78 \end{array}    (a) On the network above, show ES, EF, LS, and LF for every event.  (b) Below, construct a Gantt chart for the network using only ES's and EF's.    (C)Using costs from the table and the Gantt chart in (b), show weekly costs for the project.    (d) Below, using the chart in (c) as a guide, construct a chart showing estimated cumulative project expenditures.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions