Doing a project fast has the following advantages:
A) achieving benefits sooner.
B) reduced risk of stakeholders' needs changing.
C) guarantees success since all projects have a predetermined due date.
D) all of the above.
E) (a) and (b) above.
Correct Answer:

Verified
Correct Answer:
Verified