Multiple Choice
The early expected start time, ES, of an activity depends on the completion:
A) of the latest EF of all of the immediate predecessor activities
B) of the earliest EF of all of the immediate predecessor activities
C) neither a nor b
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q7: In a network, the critical path indicates:<br>A)
Q8: The critical path:<br>A) is shortest path through
Q9: The forward and backward pass:<br>A) determine the
Q10: If an activity has two immediate successors
Q11: Use the table and network below
Q13: Statement: The term "dummy activity" is a
Q14: Statement: If an activity has multiple predecessors,
Q15: In a network, the critical path is
Q16: Level the resources for the activities below:
Q17: Which one of the following statements is