Multiple Choice
The following technique requires the use of "dummy" activities:
A) the Gantt chart.
B) the AON network method.
C) the AOA network method.
D) the critical chain method.
E) all logic diagramming methods.
Correct Answer:

Verified
Correct Answer:
Verified