In a Start-To-Start Relationship, a 2-Day Lag Implies That

Question 21

Multiple Choice

In a start-to-start relationship, a 2-day lag implies that:


A) the successor should not start until two days after the predecessor has been completed.
B) the successor should not start until two days after the predecessor has started.
C) the successor can start two days before the predecessor has started.
D) the two activities can start on the same date.

Correct Answer: