Multiple Choice
In a start-to-start relationship, a 2-day lag implies that:
A) the successor should not start until two days after the predecessor has been completed.
B) the successor should not start until two days after the predecessor has started.
C) the successor can start two days before the predecessor has started.
D) the two activities can start on the same date.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: Level the resources for the activities below:
Q17: Which one of the following statements is
Q18: Doing a project fast has the following
Q19: Statement: The total slack of each of
Q20: Statement: The free slack of each of
Q22: The following technique requires the use of
Q23: If an activity has two immediate predecessors
Q24: The criticism of network techniques that some
Q25: Resource leveling:<br>A) makes use of float (slack)
Q26: Statement: There can only be one critical