Short Answer
Use the following Gantt chart and table to answer questions (a) and (b).
(a) On this diagram, show the total daily workers required (loading) assuming early start times for all activities. Show what portion of the total labor loading each day comes from each activity.
(b) On this diagram, balance the loading of workers by shifting activities so that no more than 20 workers per day are needed. Assume that the project must be completed in eight days.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: The advantages of scheduling include all of
Q2: If Activity A has to be performed
Q3: Statement: Redundant activities are activities that are
Q5: The latest allowable finish time that an
Q6: In the PDM method (circle all that
Q7: In a network, the critical path indicates:<br>A)
Q8: The critical path:<br>A) is shortest path through
Q9: The forward and backward pass:<br>A) determine the
Q10: If an activity has two immediate successors
Q11: Use the table and network below