menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management for Engineering
  4. Exam
    Exam 7: Project Schedule Planning and Networks
  5. Question
    In a Network, the Critical Path Indicates
Solved

In a Network, the Critical Path Indicates

Question 7

Question 7

Multiple Choice

In a network, the critical path indicates:


A) the shortest possible time in which the project can be done
B) the longest possible duration of the project
C) neither (a) nor (b)
D) both (a) and (b)

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q2: If Activity A has to be performed

Q3: Statement: Redundant activities are activities that are

Q4: Use the following Gantt chart and table

Q5: The latest allowable finish time that an

Q6: In the PDM method (circle all that

Q8: The critical path:<br>A) is shortest path through

Q9: The forward and backward pass:<br>A) determine the

Q10: If an activity has two immediate successors

Q11: Use the table and network below

Q12: The early expected start time, ES, of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines