Multiple Choice
The forward and backward pass:
A) determine the early and late start dates of activities, respectively.
B) determine the float (slack) of activities.
C) determine the critical path.
D) all of the above.
E) (a) and (c) above
Correct Answer:

Verified
Correct Answer:
Verified