Multiple Choice
You are the CEO receiving a report for a crucial, high visibility project, The Omega Project. Your PM reports that Omega's schedule performance index (SPI) is sitting at 1.28 and cost performance index (CPI) at 0.88. What would you say describes Omega's status?
A) Omega is ahead of schedule and within its budget
B) Omega is behind schedule and within its budget
C) Omega is well ahead of schedule, but over-budget
D) Omega is right on schedule, but it is running over-budget.
E) Omega is behind schedule and over-budget
Correct Answer:

Verified
Correct Answer:
Verified
Q12: When is the project manager using analogous
Q13: What does the 50/50 rule of progress
Q14: This is based on a real scenario
Q15: What is a murder board? Select all
Q16: What is true of corrective action?<br>A)Action against
Q17: What does the 20/80 rule of progress
Q18: The lower the better for Schedule Performance
Q19: Which of the following is NOT true
Q20: Which situation below would most negatively impact
Q22: Which of the following is common problem