Multiple Choice
Which situation below would most negatively impact Rick's personal integrity as a Project Manager?
A) Rick has inadvertently made a mistake on a status update.
B) Rick accepted a lunch invitation from a contractor he does business with.
C) Rick got frustrated with some team members, lost his temper and shared with them a few "choice" words.
D) Rick allowed a new deliverable to be added to the project, because it would have piggy-backed easily off of another deliverable.
E) These are all fine.