Multiple Choice
Which of the following is common problem in project management that is a typical result of unrealistic time estimates by the project manager?
A) Fast tracking
B) Critical chain
C) Schedule compression
D) Employee changes
E) Crashing
Correct Answer:

Verified
Correct Answer:
Verified