Solved

Kennedy Is Utilizing the Precedence Diagramming Method to Spec Out

Question 2

Multiple Choice

Kennedy is utilizing the Precedence Diagramming Method to spec out the first phase of his project at the Tiny Titans Tech Company. This phase of the project involves starting the design for a new website, but he must wait four weeks before he can upload any content. Which method best describes the relationship between these activities?


A) Finish-to-start
B) Start-to-start
C) Finish-to-finish
D) Start-to-finish

Correct Answer:

verifed

Verified