Multiple Choice
Terry is managing a project at a top construction firm. Her project team includes Tammy and Sal. She's also in constant contact with Burt (her client) , Ben (her Direct Manager) and Peter (PMO Officer) . Who are the stakeholders in this project?
A) Terry, Burt
B) Terry, Burt, Tammy, Sal
C) Burt, Peter
D) Terry, Tammy, Sal, Burt, Ben, Peter
E) Terry, Tammy
Correct Answer:

Verified
Correct Answer:
Verified